Bulk Actions allow users to take the same action on multiple items at a time within a module to which the user has access to via their assigned user group.

...

Table of Contents
minLevel1
maxLevel7

Work Order Lines

When on the Work Order screen, scroll down to see the Work Order Lines. The option is called “Bulk Actions”

...

The Actions that can be used are Assign and Close

Bulk Assign

This option allows the user to select multiple work order lines and assign the selected lines to a technician in one fell swoop.

Click on Bulk Actions > Bulk Assign > Click the checkbox for each line you wish to assign to a certain Technician.

Bulk Close

This option allows the user to select multiple work order lines and close those lines, as long as all closing requirements are met.

...

Once the issues are resolved (the notes are properly inputted), use the Close button at the bottom to finish each line. Once all issues have been resolved, the lines will be closed.

PMs Due

Refer to PMs Due List for more information on this list in RTA Web.

...

Info

Line items already assigned to an open WO awaiting completion will not be available to select.

...

Assign Jobs

You can release, re-assign, and remove scheduled job hours using the bulk action feature in Assign Jobs under the Shop module.

Refer to Assign Jobs for more information on this area in RTA Web.

  1. To start the process, click the Bulk Action button at the top and choose the type of action you will be doing in bulk.

  2. Once selected, the selection boxes at the start of each line item will display and you can select the number of lines to be included in the action.

  3. After all items are selected to be included, click the bulk button at the top again.

...

Requests

Use the bulk actions to auto create purchase orders from requests for multiple or all items at a time.

...