Purchase Order Lines

If PO Approvals are in use, an approved PO that has changes made will have to be approved again before able to be processed and post received items.

Adding a Line to a PO

Lines can be added to a PO using the following process:

  • Click the Add Line link in the Line Info Tab

  • Select an available part number from the drop down or enter in a part not on file and NONFILE will display to the right of the dropdown

    • A part on file will have all relevant fields from the part file pull into the details for the PO

    • If alternate part #s have already been set up/associate with the main part file number, typing those in will reference and allow the user to pull the part number based on that alternate number

  • Add an alternate part # if needed and this is generally a vendor cross reference number if the vendor’s part number differs from the main file part number assigned in RTA

     

     

  • Once the part number is pulled into the line, a user can associate an Alt Part# with the main part file by clicking in the Alt Part # field, entering the alternate part number, and clicking the check mark

    • This number will now cross-reference the main part file number and can be used in the future to locate the main part file number when adding a line to a PO

  • Description: If the part in on-file then the description will pull automatically from the part record. If it is NON-FILE then you can put in a Description of the part on the PO line

  • Add the Order Quantity

  • Add or Edit the Order Price depending on what is displayed

  • Add a Tax Rate if necessary (one may already be present if a tax rate has been set up in the vendor file or facility file)

  • Add Freight charge if necessary

  • If the switch to use account numbers is turned on and the part being added to the line has an account number assigned as part of it’s file, that account number will fill in automatically

    • If the part file does not have an account number listed, the system will use the default account number set up in the system switches

  • Add a Work Order Number if the part being ordered will be posted directly to an active work order upon receipt

    • Also add the Work Order Number and Line Number of the assigned work order where the part will post upon receipt

  • Add any pertinent Line Notes needed for the order

  • Click the Add button in the bottom footer section

Line Total

  1. The line total will remain 0 until the line item has been received.

  2. Once the line has been reviewed, you may click Received and you will have the option to receive to inventory or add to Work Order.

  3. Once the line item has been received, the Line Total will display for that particular line.

 

Editing an Existing PO Line

  1. To edit a line, click on the line

  2. Click the edit link in the Line Info Tab

  3. Edit necessary fields that are editable

 

Denotes editable fields.

  • Part Number

  • Alt Part #

  • Description (If it is a NONFILE Part)

  • Order Unit Quantity

  • Order Price

  • Tax Rate

  • Freight

  • Account Number

  • WO Number/Line

Deleting an Existing PO Line

Deleting a PO line will remove the lines from the PO, but still show a record of them having existed at one point. After deletion, the only action available will be to undo deletion.

To delete a line, click on the line in the PO and click Delete.

A bulk action can also be used by clicking the Bulk Actions link and selecting Bulk Remove. Then just select the lines to be removed.

 

Moving Existing PO Lines

This action will move lines to a new PO, delete the current OPEN lines from the current PO, or if there is partial received quantity, it will transfer the remaining on order items to a new PO. If it is a blanket PO, there are extra options available for what to do with the blanket.

Moving Lines - PO Numbers Created by RTA Automatically

  1. Highlight the line to be moved

  2. Click Move

  3. Read the prompt and click Move or Enter in the PO number to be used and click Move again

Moving Lines - PO Numbers Created at Company Level

  1. Highlight the line to be moved

  2. Click Move

  3. Read the prompt

  4. Enter the new PO# the lines will be moved to

  5. Click Move

Moving Lines for Blanket PO

  1. Highlight the line to be moved

  2. Click Move

  3. Read the prompt (will display the next blanket PO extension to be used)

  4. Click Use Blanket PO

 

 

Related Articles:

 

Work Orders

PO Approvals

Blanket POs

Receiving Lines